Public works Department (Roads)

 

1.    PWD Annual Plan:

 

          Under PWD Annual Plan, 2001-02, 11(eleven) nos. of Road Schemes were taken up and completed with total fund involvement of Rs. 194.09 lakhs. Total amount spent for completion of the works was Rs. 192.75 lakhs.

 

          The status of the Road Schems during 2001-02 is indicated below:-

 

Sl. No

Name of the Scheme/Programme

Total Fund Involved

(Rs. In lakhs)

Total Expenditure Incurred

Physical Progress

1

NG Mandakata road

21.49

21.20

100%

2

Dumunichowki Saraighat Ulta. Simlibari Road

25.00

25.00

100%

3

Rangmahal Changsari road

21.93

21.25

100%

4

Matakher Road

10.00

10.00

100%

5

P.L. Rajapara Road

10.00

10.00

100%

6

Rajapara Borigaon Road

10.00

10.00

100%

7

Rajapara Chandubi road

10.00

10.00

100%

8

Muduki Longsai Road

10.00

10.00

100%

9

Hekra Nagarbera Road

28.99

28.90

100%

10

Singra Hekra Road

24.76

24.50

100%

11

Fullung Lenga Road

21.92

21.90

100%

 

Total

194.09

192.75

--

 

          Under PWD Annual Plan 2002-2003, 8(eight) nos. of Road Schemes taken up and completed with total fund involvement of Rs. 179.00 lakhs.

          The Status of the Road schemes during 2002-03 in indicated below:-

 

Sl. No

Name of the Scheme/Programme

Total Fund Involved

(Rs. in lakhs)

Total Expenditure Incurred

(Rs. in lakhs)

Physical Progress

1

Dalibari Muslimsupa Road

20.00

20.00

100%

2

Pacharia Sigimari Road (Collage Approach)

24.00

24.00

100%

3

Rangmahal Changsari Road

20.00

20.00

100%

4

Gandhmou Bangshar Road

22.00

22.00

100%

5

Gogmunchiali Road

22.00

22.00

100%

6

Athiabari Bonmaja Road

24.00

24.00

100%

7

Bhetamukh to Baralabari Road

22.00

22.00

100%

8

Pizupara Hariduva Road

25.00

25.00

100%

 

Total

179.00

179.00

--

 

         

 

 

          Under PWd Annual Plan, 2003-04, 16(sixteen) nos of total Scheme have been taken up with total fund involvement of Rs. 856.042 lakhs, out of which an amount of Rs. 746.00 lakhs has been spent. Out of 16 nos of Schemes, works selecting to 11 nos. of Schemes have been already been completed. Remaining 5 nos. of Schemes are ongoing under Annual Plan, 2003-04.

 

          The Status of the Schemes during 2003-04 is indicated below:-

 

Sl. No

Name of the Scheme/Programme

Total Fund Involved

(Rs. in lakhs))

Total Expenditure Incurred

(Rs. in lakhs)

Physical Progress

1

Sigra Hekra Road

50.0

50.00

100%

2

Bamunigaon Santipur Road

50.00

50.00

100%

3

Pizupara Haridova Road

25.00

25.00

100%

4

Mandira Nichalamari Road

25.00

25.00

100%

5

Inspection Benglow at Amingaon

27.464

27.50

100%

6

Fulung Lenga raod

18.62

18.50

100%

7

Arjantal Bhomlahati (Bezsupa) Road

30.02

30.00

100%

8

Sualkuchi Purbanchal Road

106.73

80.00

95%

9

Gandhmow Bangshar Road

79.812

70.00

98%

10

Changsari Nathgaon Road

39.115

10.00

50%

11

North Guwahati Ferry approach Road

165.87

165.00

100%

12

Dhopatari Silabharal Muslimsupa Rd.

5.176

5.00

100%

13

n.G. Mandakata Road

107.16

100.00

100%

14

Bhurgaon Helagog Road

50.00

50.00

100%

15

Amingaon Hariapatty Road

26.075

15.00

90%

16

Pakhamela road

50.00

25.00

50%

 

Total

856.042

746.00

--

 

          Under PWD Annual Plan, 2004-05, 5(five) nos of total Scheme have been taken up with total fund involvement of Rs. 159.58 lakhs, out of which an amount of Rs. 49.90 lakhs have already been spent. Out of five nos. of Schemes, one scheme has already been completed.

 

          The Status of the road Schemes during 2004-05 is indicated below: -

 

Sl. No

Name of the Scheme/Programme

Total Fund Involved

(Rs. in lakhs)

Total Expenditure Incurred

(Rs. in lakhs)

Physical Progress

1

Simlitola Nagarbera Road

29.00

Nil

60%

2

Mandira Nichalamari Road

30.00

Nil

50%

3

Nagarbera Namasadrapara road

21.00

Nil

40%

4

Batorhat Chimina road

49.98

49.90

100%

5

Mirza Lowershipment Raod

29.60

Nil

--

 

Total

159.58

49.90

--

 

 

 

 

 

  1. Central Assistance Scheme:

 

          Under Central Assistance Scheme for 2002-03 one road sheme, namely, Barkhat Borni Road with the total fund of Rs. 469.74 lakhs has been taken up and 85% progress has been achieved.

3. Centrl Road Fund:

          Under Central Road Fund for 2001-2002, one road scheme, namely, Singimari Bongshar Sualkuchi road with the total fund of Rs. 696.26 lakhs has been taken up and 99% of the works have been completed with a total expenditure of Rs. 605.50 lakhs.

 

          Under Central Road Fund for 2002003, one road scheme, namely, PL Rajapara PWD road with the total fund of Rs. 350.00 lakhs has been taken up and 90% of the works have been completed with the total expenditure of Rs. 234.00 lakhs.

 

3.    RIDF-IX for 2004-05

 

          Under RIDE-IX for 2004-05, construction work of 7 nos. of RCC Bridges have been taken up and the works are in progress. The bridges have been started on Kendukona-Changsari Road(two bridges), Hekra-Nagarbera Road,Chaygaon -Gumi road, Palashbari-Loharghat-Rajapara Road and Rangmahal-Changsari Road (two bridges), total fund involved against the bridges is Rs. 868.01 lakhs.

 

4.    NLCPR for 2004-05:

 

          Under NLCPR for 2004-05, construction works of two nos. of RCC Bridges have been taken up with a total cost of Rs. 224.24 lakhs.

 

6. MPNA for 2004-05:

          Under MPNA for 2004-05, 8(eight) nos. of roads have been taken up for construction with total fund involvement of Rs. 978.56 lakhs.

 

*****

 

 

Acievements under PMGSY works in Kamrup district

during last four years w.e.f. 2001-02

 

          The Achievements under PMGSY works in Kamrup district are indicated below:-

 

A) PMGSY Roads, 2001-02

 

                   i) Total sanctioned estimated Amount       :         Rs. 723.57 lakhs

                   ii) Up to date expenditure                 :         Rs. 662.23 lakhs

                   iii) Total nos. of Packages taken up          :         5 nos.

                   iv) Total nos. of roads taken up       :         12 nos.

                   v) Total road length covered            :         26.575 kms.        

                   vi) Total no. of CD works completed        :         i) HPC :      28 nos.

                                                                                       ii) RCC bridge: 1 no.

1.    Package No. AS-1101/2001-02

 

Sl. No.

Name of Roads

Physical Progress

(Percentage)

1

Panitema-Kendukona Road

100%

2

Behapara Kaurbaha Road

100%

3

Naokata-Suagpur road

100%

 

 

 

 

 

          2. Package No. AS-1102/2001-02

 

Sl. No.

Name of Roads

Physical Progress

(Percentage)

1

Dhupartal-Majuli road

100%

2

Chandrapur-Missamari Road

100%

 

3 Package No. AS-1103/2001-02

 

Sl. No.

Name of Roads

Physical Progress

(Percentage)

1

Jharubari-Jogi Road

100%

2

Naukuchi-Markong Road

100%

 

4       Package No. AS-1104/2001-02

 

Sl. No.

Name of Roads

Physical Progress

(Percentage)

1

Hajo Chapari-Ramdia Halogaon Road

100%

2

Rowmari Pakorkona Road

100%

3

Similibari -Saraighat Road

100%

 

5.    Package No. AS-1105/2001-02

 

Sl. No.

Name of Roads

Physical Progress

(Percentage)

1

Hekra Jogipara Road

100%

2

Barkhat-Tarigaon Road

100%

 

 

 

 

 

 

B) PMGY Roads, 2002-03 (Fund not provided)

 

C) PMGSY roads, 2003-04

 

                   i) Total sanctioned estimated Amount       :         Rs. 1696.30 lakhs

                   ii) Up to date expenditure                          :         Rs. 1086.40 lakhs

                   iii) Total nos. of Packages taken up                   :         7 nos.

                   iv) Total nos. of roads taken up                 :         9 nos.

                   iv) Total road length to be covered  :       60.387 kms.

                   v) Total no. of CD works completed  :     HPC: 107 nos, RCC bridge: 11nos.

Sl. No.

Package No.

Name of Roads

Physical Progress

(Percentage)

(1)

(2)

(3)

(4)

1

AS-1106/2003-04

Boko Chamaria via alekjari Road

78%

2

AS-1107/2003-04

Gouripur to Bezera Road

85%

3

AS-1108/2003-04

Murara Kelenchuk Road

63%

4

AS-1109/2003-04

Kamalpur Borka Road

92%

5

AS-1110/2003-04

Hajo Ramdia Hologaon Road

45%

6

AS-1111/2003-04

i) Kalutali to Goroimari road

100%

ii) Boko Pairanga Road

100%

7

AS-1112/2003-04

i) NH-31 to Banglamara Road

95%

ii) Dhopguri to Ouguri Road

50%

 

D) PMGSY Roads 2004-05

                   i) Total sanctioned estimated Amount       :         Rs.    1702.45 lakhs

                   ii)Up to date expenditure                  :         414.00 lakhs

                   iii)Total nos. of Packages taken up           :         8 nos.

                   iv)Total nos. of roads taken up        :         15 nos.

                   v) Total road length covered            :         51.179 kms.

                   vi) Total no. of CD works completed        :         HPC=68 nos, RCC=3nos.

 

Sl. No.

Package No.

Name of Roads

Physical Progress

(Percentage)

(1)

(2)

(3)

(4)

1

AS-1113/2004-05

i) Jogipara to Silobari Road

63%

ii) Dakuapara to Raipara Road

50%

2

AS-1114/2004-05

i) Passomtola to Pachimdhuli Road

42%

ii) Agumi to Hatipara Road

41%

3

AS-1115/2004-05

i) Sualkuchi to Bamundi Road

15%

ii) Hajo to Ukhura Road

Just Started

4

AS-1116/2004-05

i) Bakrapara to DK Vidyapith H.S. Road

45%

ii) Nahira to Guimara Road

45%

5

AS-1117/2004-05

i) Rani to Garal Road

12%

ii) Naukuchi to Markong Road

32%

6

AS-1118/2004-05

i) Sualkuchi to Srihati Road

22%

7

AS-1119/2004+-05

i) Baihata to Barka via Boragog Road

20%

ii) Rangia to Hajo via Rangia College

30%

8

AS-1120/2004-05

i) Murara to Boronghati Road

30%

ii) Rangia to Dhamdhama Road

25%

 

PMGSY Roads 2005-06

 

                   i) Estimates submitted for                :         Rs.    2692.65 Lakhs

                   ii) Total nos. of Packages taken up           :         12 nos.

                   iii) Total nos. of roads taken up       :         21 nos.

                   iv) Total length to be covered          :         71.98 kms.

                   v) Up to date position                       : All DPR under process of sanction.

 

N.B. Progress report has been prepared on the basis of Report Submitted by S.E. PwD (Roads), Guwahati vide letter No. T/COM/2002/53/pt/1760 dated 13-06-05.